At NEOS Engineering Services, we take pride in our reputation as a trustworthy name in the precast design and detailing industry. Our recent work in Hampshire is a testament to our efficiency and dedication. We were tasked with producing structural drawings for culverts that support three bridges in Hampshire. These crucial components required detailed attention to ensure their structural integrity and durability. Here are the details of the three bridges:
Bridge 1:
- Precast Units: 13
- Total Weight: 110 Tons
- Concrete Volume: 43.75 m³
- Drawings Produced: 1 General Arrangement, 8 Shop Drawings
Bridge 2:
- Precast Units: 15
- Total Weight: 130 Tons
- Concrete Volume: 52.10 m³
- Drawings Produced: 1 General Arrangement, 8 Shop Drawings
Bridge 3:
- Precast Units: 13
- Total Weight: 130 Tons
- Concrete Volume: 54.44 m³
- Drawings Produced: 1 General Arrangement, 10 Shop Drawings
Execution
It took us exactly 150 hours to complete the entire project. From conception to execution, our commitment at NEOS remained steadfast, only increasing as we moved forward. This project is proof of our efficiency and the accuracy of our approach.
Efficiency and Outcomes
As a result of our precise planning and streamlined processes, we achieved significant improvements
Work hours reduced
We reduced working hours by 40%. Accurate planning and timing positively impacted the project without overspending resources or manpower, allowing for timely delivery without compromising quality.
Manpower reduction
We reduced manpower by 30%. Fewer people to supervise meant an increase in revenue, allowing us to judiciously utilize resources.
Cost savings
We achieved a 25% reduction in overall project costs through optimized processes and reduced material waste. We delivered cost-effective solutions without compromising quality.
Error reduction
We reduced errors by 80%, ensuring that all culvert components fit together perfectly, eliminating the need for reworks.
Material waste reduction
We reduced material waste by 20% through error reduction during production, aligning with our commitment to sustainability.
Improved collaboration
We saw a 25% improvement in coordination and collaboration, leading to smoother workflows and better communication among all stakeholders.
Increased client satisfaction
Our clients reported a 25% increase in satisfaction due to the project’s seamless execution and high-quality outcomes.
Conclusion
The Hampshire culvert bridge project stands as proof of our commitment to client satisfaction and quality work at NEOS. Our efficiency and precision enabled us to deliver exactly what the client asked for, with speedy delivery and no compromise on quality. At NEOS, we continually push the boundaries of structural engineering with our dedication, exceeding expectations and upholding environmental ethics and sustainability in our work.